Projects in Design/Construction

PANHANDLE REGION

Farragut WMA:

– A project to construct a new bunkhouse and RV pads is in the design stage on the Farragut WMA. Construction is planned for summer 2019.

– A project to construct a new Hunter Ed classroom at the Farragut Shooting Range is in the design process. Construction is planned for summer 2019.

McArthur Lake WMA:

– A project at Kootenai Sturgeon Field Station at McArthur Lake to relocate a double wide trailer bunkhouse in 2019. A concrete pad and utilities were constructed for the bunkhouse. A new boat shed will be designed and constructed in 2019 and a site prepped for a new field office.

Black Rock Slough:

– A project to construct new water control structures at the subject site. The design has been completed. The design is to be submitted to a contractor to obtain a construction estimate so that the region can acquire the necessary funding for construction in fall 2019.

Clark Fork River Delta:

– A project to improve habitat on the Clark Fork River Delta is in the design and construction solicitation stage. The approximate $4 million dollar project is anticipated to begin fall of 2019.

CLEARWATER REGION

     No current Public Works Projects

SOUTHWEST REGION

Headquarters Administration Building:

– A feasibility analysis has begun to identify future space needs and determine budget for a new Headquarters Building.

Horsethief Reservoir:

– Kings Point site. Idaho Parks & Recreation grant obtained to improve camp sites by paving loop road, vehicle parking spots, and parking area for boat ramp; installing drainage facilities; constructing camp pads and sidewalk for ADA access; and adding picnic tables. Design complete. Construction anticipated in summer 2019.

– Osprey Bay and Easter Cove campgrounds on west side of reservoir. Includes paving roads, parking area, and camp spots; and installing picnic tables and fire rings. Concept drawings and cost estimates are complete. Region has submitted grant application to State Parks and Recreation Dept. for funding.

Boise River WMA:

– A project to construct shop/office building at WMA Headquarters. Construction is substantially complete. Minor punch list items to be completed when ground thaws. Anticipate final completion in March 2019.

Blacks Creek Rifle Range:

– A project to construct a new Multi-Purpose building has reached substantial completion. The contractor is completing a few small items on-site.

– A project to lower the profile of the long distance shooting range and use the excavated material to build up the berms along the east side of that range is in the design stage.

Plaza Bridge:

– A project to improve gravel parking area and road approach, install restroom pad and kiosk, and block public access to specific roads on the property is complete.

Letha Ramp:

– A project to install new concrete block boat ramp, gravel parking area, fencing, and road approach is complete.

Emmett Segment Bank Repair:

– A project to remove and replace a temporary bank repair with a more permanent solution is complete.

Gem Island Ramp:

– A project to install a new concrete boat ramp at county park entrance. Project is in the design phase. The Region is working on permitting and county approvals. Construction anticipated in fall/winter 2019.

7-Mile Slough Boat Ramp:

– A project on Payette River near Emmett to install a new concrete boat ramp, improve gravel parking area, install restroom pad and kiosk, and install boulders. Construction of gravel parking area, restroom pad, and kiosk and boulder installation is complete. Boat Ramp portion is in design phase and construction is anticipated to begin in fall/winter of 2019.

Andrus WMA Residence:

– A project to replace old residence with new modular home. Project is in the design/bid phase. Construction anticipated in spring/summer 2019.

CJ Strike WMA Residence:

– A project to construct a new stick frame residence on WMA property. Project is in design phase. Construction anticipated in summer 2019.

Garden Valley House Remodel:

– A project to remodel existing residence to create more usable living space. Project is in the design phase. Construction anticipated in fall 2019.

McCall Regional Office:

– Remodel interior. Includes partition walls for offices, cabinets, and painting. Contractor has been selected and construction has begun. Completion anticipated in April 2019.

Fort Boise WMA:

– A project to replace Four CMP Culverts on the sand hollow canal at the Old Fort Boise Road crossing with new culverts. Construction scheduled to begin in late-February and be complete by late-March.

Nampa Hatchery Residence:

– A project to construct a new modular home. Project is in the design/bid phase. Construction anticipated in summer 2019.

Payette River WMA Irrigation Structure:

– A project to install automated gates in existing concrete structure to maintain constant upstream water level in canal. Gates will prevent flooding of neighbor’s fields. Project in design phase with Construction anticipated in Fall 2019.

MAGIC VALLEY REGION

Hammett Boat Ramp:

– A project to install new concrete boat ramp, gravel parking area, and gravel roads. Project is in the design phase. Region working on permitting and county approvals. Construction anticipated in summer 2019.

Magic Valley Regional Office:

– A project to remodel the existing shooting range into a classroom is in the construction phase. First Phase Construction anticipated to be complete in March 2019.

SOUTHEAST REGION

Eagle Rock Boat Access site:

– A project to repair gravel road to site. Work includes excavation, grading, fill material, drain ditches, culvert, then placing and compacting surface gravel. Region in the process of obtaining easements for work on the road from Idaho Dept. of Lands and Bureau of Reclamation. After easements are obtained, final design will be needed. Unknown construction timeline.

American Falls Hatchery Residence:

– A project to construct a new modular home and detached garage. Project is in the design/bid phase. Construction anticipated in summer 2019.

Grace Hatchery Residence:

– A project to construct a new modular home and detached garage. Project is in the design/bid phase. Construction anticipated in summer 2019.

UPPER SNAKE REGION:

Tex Creek WMA:

– A project to construct (replace) approximately 3 miles of fence (lost during the 2016 fire) has been contracted. Construction anticipated in spring/summer of 2019.

Idaho Falls Regional Office:

– A project to install new door access control and camera security has been completed.

– A project to remodel the front desk areas of the Regional Office has been completed.

Mud Lake WMA Shop:

– A project to construct a new shop on the WMA is under construction and is 95% complete. Anticipate completion of this project by early March 2019.

Mackay Hatchery Residence:

– A project to construct a new modular home. Project is in the design/bid phase. Construction anticipated in summer 2019.

SALMON REGION:

Upper Salmon Basin Fish Habitat Improvements:

– The region is working with consultants to design and construct stream restoration projects throughout the Upper Salmon Basin.